Purchase Orders
Purchase Order reference
PO-2026-0002In Production
Summary
- Project reference
- PRJ-A1001
- Source Request for Quotation
- RFQ-2026-0008
- Purchase Order date
- 22 Sept 2026, 09:15 UTC
- Total amount
- USD 10,177.50
- Parts
- Impeller IM-55 × 150
- Wear ring WR-55 × 300
Next step
Production is underway. Watch the milestones for delays.
Last update: 19 Oct 2026, 09:15 UTC
Production
Expected shipment 7 Nov 2026 (Estimated)Revised date: Revised from the original estimate because machining is delayed.
Material preparation
Impeller IM-55
Done- Planned
- 25 Sept 2026 – 2 Oct 2026
- Actual
- 25 Sept 2026 – 1 Oct 2026
Machining
Impeller IM-55
In progress4 days late- Planned
- 3 Oct 2026 – 18 Oct 2026
- Actual
- 4 Oct 2026 – …
- Reason for delay
- Five-axis machine maintenance (synthetic example).
Machining
Wear ring WR-55
In progress- Planned
- 7 Oct 2026 – 25 Oct 2026
- Actual
- 8 Oct 2026 – …
Surface finishing
All parts
Not started- Planned
- 26 Oct 2026 – 1 Nov 2026
- Actual
- —
Delay counts calendar days after the planned end for unfinished work, in the business timezone (UTC). Production plans are read-only for buyers.
Clarifications
- Impeller balance gradeAwaiting reply
Supplier · 16 Oct 2026, 08:15 UTC
Can you confirm balance grade G6.3 is acceptable?
You · 17 Oct 2026, 16:15 UTC
Yes, G6.3 is acceptable.
- Please record it in the report.